WORKITEMS | DESCRIPTION | COMMENT | ASSIGNED TO | START DATE | END DATE | STATUS | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
REF15-3A | Update of VO / group management needs assessment documents. | Available on the REFEDS wiki. | Heather Flanagan | 04/2015 | 12/2015 |
| ||||||
REF15-3B | VO / Groups Problem Statement Document | Overview presented at Cleveland meeting, paper to be prepared. | Heather Flanagan | 04/2015 | 12/2015 |
| ||||||
REF15-3C | Value Proposition of federations for VOs document. | Draft available on REFEDS wiki. Seeking further commentary. | Heather Flanagan | 04/2015 | 12/2015 |
| ||||||
REF15-3D | 3 x conference call to discuss namespace requirements. | Work postponed until 2016. | Licia Florio | 04/2015 | 12/2015 |
| ||||||
REF15-3E | Draft proposal on standardising namespace for groups. | Work postponed until 2016. | Licia Florio | 04/2105 | 12/2015 |
|
REF15-4: REFEDS Services and Monitoring.Lead: Licia Florio |
---|
Aims:
|
WORKITEMS | DESCRIPTION | COMMENT | ASSIGNED TO | START DATE | END DATE | STATUS | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
REF15-4A | REEP Operations. | New contract with Emergya delivered, LF working to evaluate deliverables to date and make proposals moving forward. | Licia Florio | 01/2015 | 12/2015 |
| ||||||
REF15-4B | Operational version of MET. | GARR working on final service version, inc updates to MET code and hosting. Need ot put small SLA in place with GARR for availability. | Nicole Harris | 02/2015 | 06/2015 |
| ||||||
REF15-4C | Liaison work with Fed Lab. | Cross GN4-AARC-REFEDS-KANTARA Work area kicked off. Funding proposal to REFEDS received. | Nicole Harris | 04/2015 | 12/2015 |
| ||||||
REF15-4D | Incident Response Framework. | Initial charter and workplan for SIRTFI circulated with stakeholders. NH preparing consultation. Consultation out | Licia Florio / Nicole Harris | 04/2015 | 12/2015 |
|
...
WORKITEMS | DESCRIPTION | COMMENT | ASSIGNED TO | START DATE | END DATE | STATUS | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
REF15-5A | Federation at scale: work to pilot the Metadata Query Protocol within multiple federations and report on readiness to manage more complex metadata management. | New contract in place with Ian. | Ian Young | 02/2015 | 12/2015 |
| ||||||
REF15-5B | Federation at scale: review of further work needed to support large-scale metadata management, including discovery. | To do. | Nicole Harris | 02/2015 | 06/2015 |
| ||||||
REF15-5C | SAML Entity Categories: finalising RFC for core documentation. | New contract in place with Ian. New version of the document ready to be released before end 2015. | Ian Young | 04/2015 | 12/2015 |
| ||||||
REF15-5D | SCHAC development and sustainability. | All work on updating SCHAC documentation now complete. Not enough work to consider adding a further contract in place. | Heather Flanagan | 01/2015 | 06/2015 |
|
...
WORKITEMS | DESCRIPTION | COMMENT | ASSIGNED TO | START DATE | END DATE | STATUS | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
REF15-6A | Ongoing operation as usual. | Peter Schober | 01/2015 | 12/2015 |
| |||||||
REF15-6B | MARI: Manging Attribute Release in Interfederation use cases | On hold pending further discussions. Recommendation not to continue with this group. | Ken Klingenstein | 01/2015 | 12/2015 |
| ||||||
REF15-6C | Not started yet. Roland H working on workplans. | Roland Hedberg | 04/2015 | 12/2015 |
| |||||||
REF15-6D | SIRTFI | Work developing well, continuing to support. | Nicole Harris | 04/2015 | 12/2015 |
|